Our new project- Our guest house


This is the shell house next door to our home, we will turn this in to a two bed house for family and friends.

This is the story of how the house was developed.

We meet our builder on Monday 10th July 2023 and looks at what we had bought. The first step was to clear out what was there and see what services had already been installed.Our builders arrived the next day and works started.

Week one clear out

Week Two building black water tank

Week Three water system and tank

Week Four internal first slab

Week Five steps to olive grove

Week Six patio slab build

An today August 23rd the road was finally used and we now have access to the house for a car

Week Seven roof repairs

Week Eight extension and new kitchen roof

Week Nine kitchen roof and drive works

Week Ten drive works

Week Eleven Drive and steps works

Week Twelve party wall works

Week Thirteen External works and house render

Week Fourteen patio wall works

Week Fifteen first floor steel and wall render

Week Sixteen first floor installed and layout plans

Plans

Week Seventeen M&E agreed and works started

Week eighteen internal walls

Week nineteen Electrical installation

Week twenty electrical first fix completed

Week Twenty one final installation elec and pluming

Floors and walls finishing

Stairs &Wall preparation and New Drive

Internal finishing

Floors and Kitchen

Final Tiling and new Drive

Door installation Wall painting and final finishing

Final preparation for first guest

Rooms ready and pool filled

Final push with outside space