This is the shell house next door to our home, we will turn this in to a two bed house for family and friends.
This is the story of how the house was developed.
We meet our builder on Monday 10th July 2023 and looks at what we had bought. The first step was to clear out what was there and see what services had already been installed.Our builders arrived the next day and works started.
Week one clear out
Week Two building black water tank
Week Three water system and tank
Week Four internal first slab
Week Five steps to olive grove
Week Six patio slab build
An today August 23rd the road was finally used and we now have access to the house for a car
Week Seven roof repairs
Week Eight extension and new kitchen roof
Week Nine kitchen roof and drive works
Week Ten drive works
Week Eleven Drive and steps works
Week Twelve party wall works
Week Thirteen External works and house render
Week Fourteen patio wall works
Week Fifteen first floor steel and wall render
Week Sixteen first floor installed and layout plans